23 Jul 2025
⚡Idaho Power's License Application for Lucky Peak Transmission Line
Idaho Power Company; Notice of Intent To File License Application, Filing of Pre-Application Document, Approving Use of the Traditional Licensing Process
Summary
The Department of Energy announces Idaho Power Company's intent to file a license application for the Lucky Peak Transmission Line Project. The notice outlines the project's details, location, and regulatory processes, including necessary consultations with federal and state agencies regarding environmental and historical factors.
Agencies
- Energy Department
- Federal Energy Regulatory Commission
Business Impact
$$ - Med
The document outlines regulatory requirements and the formal process for Idaho Power Company to apply for a license for the Lucky Peak Transmission Line Project. Business owners must comply with the outlined processes, including consultations with various agencies, and noting that at least 24 months' notice is required before license expiration impacts project timelines.